Jobs/Whitfield — Congresbury BS49

Whitfield — air source heat pump

JOB-2291 · 14 Mill Lane, Congresbury BS49 · surveyed 4 Aug · installing 8–10 Sep

DNO approval outstanding
Contract value
£13,400
Heat pump, cylinder, 4 radiators
Customer pays
£4,400
After the grant, before finance
Stage
Pre-install
2 blockers
Estimated margin
23%
£3,082 · 3 team-days

What is holding it up

Two things, both outside Thornbeck, both with a date

BlockerWithSinceChasedNeeded byStatus
G99 connection approvalWestern Distribution 31 Jul2 times4 Sep 25 days
Signed finance agreementCustomer 12 Aug1 time1 Sep 13 days
Cylinder deliveryOrdered, confirmed 3 Sep On schedule
ScaffoldNot required n/a
The install is booked for 8 September and three team-days are held for it. If the G99 is not back by the 4th, that is three days of six people with nothing to do — which is why the date, not the application, is what the system watches.

Funding

Grant, finance and what the customer actually writes a cheque for

Contract value£13,400
Boiler Upgrade Scheme grant−£9,000
Rate appliedOff gas grid, oil
Customer contribution£4,400
Of which on finance£3,000 over 60 months
Deposit taken£1,400 · 12 Aug
Grant applicationSubmitted 6 Aug
Grant redeemed onCommissioning
Thornbeck carries the grant until commissioning. Nine jobs currently in flight are carrying £65,800 of grant between them. That is working capital, and until now nobody could put a number on it. The rate itself is derived from the property — the fuel it runs on, whether it is on the gas grid, the measure going in — and held as scheme configuration, so it moves when the scheme moves rather than when somebody remembers.

The property

Type
Detached bungalow, 1968
Floor area
112 m²
EPC
D 58 · lodged 2019 · recorded for sizing, not used to gate the grant
Heat loss
7.4 kW at −2.4°C
Current heating
Oil boiler, 2004
Loft insulation
100mm · topping to 300mm
Occupants
2 · both retired, home in the day

Customer

Enquiry18 Jul
First contact2 min
Survey4 Aug
Quote issued4 Aug, same day
Accepted12 Aug
SourceCustomer referral
Referred by a neighbour Thornbeck fitted solar for in 2024. It converted in 25 days, cost nothing to acquire, and is the third job on that street.

Survey findings and design

Captured on site by Tom Casey, 4 August

ItemFindingDesign decisionEffect on price
Heat loss7.4 kW at design temperature8 kW monobloc unitBaseline
Existing radiators4 undersized for 45°C flowReplace 4, keep 7+£1,180
Hot waterNo cylinder — combi oil210 litre unvented cylinder+£1,640
Pipework22mm to airing cupboard, adequateReuse
Unit sitingNorth-east elevation, 1.2m to boundaryMCS 020: 35.4 dB(A), passes by 1.6 dB
Electrical supply60A main fuse, board has spare waysNo upgrade needed
Loft100mm, unevenTop up to 300mm+£420
Quote issued at 17:40 the same day. Thornbeck's conversion on same-day quotes is 61%; on quotes issued a week later it is 24%.

MCS 020 noise assessment

Calculated from the positions recorded at survey

Declared sound power level
54 dB(A) · 8 kW monobloc
Assessment position
Habitable room window, No. 14
Distance
4.2 m
Reflective surfaces
One — the wall behind the unit
Barrier
None
Calculated35.4 dB(A)
Limit37.0 dB(A)
Margin1.6 dB
Three positions were tested and this is the worst of them. It passes, but 1.6 dB is tight enough to be worth moving the unit 600mm along the elevation on the day, rather than arguing about it afterwards. Tom had this before he left the drive instead of estimating it there and checking it at a desk on Monday.

Photographs

Site photos24
Consumer unitCaptured
Proposed unit positionCaptured
Loft hatch & accessCaptured
Every radiator11 of 11
The install team sees these before they load the van. Thornbeck's most expensive day is the one where a crew arrives and cannot start.
A heat pump install triggers half a dozen separate notifications, registrations and certificates, each with its own deadline and its own portal. Miss one and the grant is at risk, the warranty is not valid, or the building control notification is late.

What this job has to produce

Tracked from the day the contract is signed, not the week after handover

ObligationBodyTriggerDueOwnerStatus
MCS installation certificateMCS / certification bodyCommissioningWithin 10 daysF. AdeyinkaNot due
Boiler Upgrade Scheme redemptionOfgem, via MCS numberCommissioningOn certificateF. AdeyinkaNot due
G99 connection approvalWestern DistributionBefore install4 Sep 2026N. BevanOutstanding 25 days
Building Regulations notificationCompetent person schemeCompletionWithin 30 daysF. AdeyinkaNot due
Electrical installation certificatePart P schemeCompletionOn handoverD. TrescothickNot due
Manufacturer warranty registrationUnit manufacturerCommissioningWithin 28 daysF. AdeyinkaNot due
TrustMark lodgementTrustMarkCompletionWithin 10 daysF. AdeyinkaNot due
Workmanship warrantyInsurance-backedCompletionOn handoverF. AdeyinkaNot due
Eight obligations from one job. Multiply by 96 live jobs and it stops being something a person can hold in their head.

Install plan

Three days, one team, everything they need on the van

  • Day 1 — Tuesday 8 September
    Strip out oil boiler, first-fix pipework, cylinder in · Trescothick team of 3
  • Day 2 — Wednesday 9 September
    Unit sited and connected, four radiators swapped, electrical works
  • Day 3 — Thursday 10 September
    Commissioning, controls set, customer walkthrough, loft topped up
  • Handover pack issued
    Same day, from the portal — certificates follow as they are issued
  • Aftercare call
    14 days · has it been running as expected through a cold snap
Oil is being removed on day one. If anything stops the job after that, the customer has no heating and no hot water. Jobs that disconnect an existing heat source are flagged so they cannot start with an open blocker — which is exactly why the G99 date matters.

Handover pack

MCS certificateOn commissioning
Electrical certificateOn completion
Building Regs noticeWithin 30 days
Warranty documentsOn registration
How to run itReady
Aftercare contactReady
Each document appears in the customer's portal the moment it is issued, rather than arriving as a wallet of paper six weeks later.