Consultations/Kingsley Mansions — roof covering renewal

Section 20 consultations

Every stage carries a statutory date. The clock below is the record of what was served, to whom, and when.

Kingsley Mansions — roof covering renewal

S20-2026-041 · qualifying works · 44 contributing units · Kingsley Mansions RTM Company Ltd

Stage overdue

Notice of Intention

Describes the works in general terms, states why they are necessary, and invites written observations. The notice must reach every contributing leaseholder and any recognised tenants' association.

Date served
14 July 2026
Method
First class post to all 44 · email in addition to the 38 who have consented to electronic service
Recipients
44 leaseholders · 1 recognised tenants' association
Deemed served
16 July 2026 — two working days after posting
Observation window
14 July – 14 August 2026 (31 days)
Prepared by
R. Nkemelu

Service evidence

  • Notice of Intention.pdf
    Generated 14 Jul 2026 · 3 pages
  • Dispatch schedule.csv
    44 addresses · certificate of posting attached
  • Electronic service consents
    38 of 44 consented · 6 served by post only

Observations received

Every observation must be logged and had regard to. The response recorded here is what the tribunal would ask to see.

UnitLeaseholderReceivedObservationResponse
Flat 4M. Farrow22 JulQueries whether scaffolding can avoid the rear light wellsAnswered 24 Jul
Flat 11A. Devlin28 JulRequests a fourth estimate from a contractor of their choosingNominee invited
Flat 17P. Osei2 AugObjects to the timing — asks for deferral to next financial yearAnswered 6 Aug
Flat 23Wrenfield Estates Ltd9 AugAsks for the full specification and the surveyor's condition reportDocuments sent
Flat 29L. Brannigan12 AugRaises affordability and asks about payment by instalmentsAwaiting reply
Flat 38C. Ilori14 AugSupports the works, asks that the aerial be reinstatedAnswered 15 Aug
This stage is 6 days past its date. Until the Statement of Estimates is served and the second observation period has run, the amount recoverable from each leaseholder is limited to £250 — against an estimated £4,180 per unit. £173,000 of the £184,000 is currently unrecoverable. The only route back is an application to the First-tier Tribunal (Property Chamber) for dispensation under s20ZA, which is neither quick nor certain and is usually made at the applicant's own cost.

Estimates received

ContractorSourceEstimatePer unitStatus
Calderwood Roofing LtdMarlbourne panel£184,000£4,182Received 8 Aug
Stapleton & RoweLeaseholder nominee£196,400£4,464Received 19 Aug
Hollis RoofingMarlbourne panelChased twice
The estimate from the leaseholder's nominated contractor must be included whether or not it is the cheapest.
Marlbourne's policy is to serve on two estimates rather than miss the date, and to issue the third by addendum if it arrives. The system will not let the stage close without recording which route was taken and who authorised it.

What happens on serving

  • Statement generated
    Estimates, specification and observations summary merged into one document
  • Served on 44 leaseholders
    Post and email · certificate of posting retained
  • Second observation period opens
    30 days · closes 9 Oct 2026
  • Recoverability restored
    Cap lifts once the period has run and observations are answered

Second observation period

Opens on the day the Statement of Estimates is served and runs for 30 days. Observations received during it must be answered before a contract is awarded.

Not started This period opens automatically when stage 3 is served. Nothing to do here yet.

Award of Contract

Where the chosen contractor is neither the cheapest nor a leaseholder nominee, a notice stating the reasons must be served within 21 days of awarding the contract.

Not started Available once the second observation period has closed.

All live consultations

7 in progress across the portfolio · £1.24m of qualifying works

Consultation Building Stage Value Per unit Next date Status
Roof covering renewalS20-2026-041 · Works £250 Kingsley Mansions £184,000 £4,182 28 Aug 2026 6 days late
External redecoration, cyclicalS20-2026-038 · Works £250 Ashwood Court £96,500 £2,681 7 Sep 2026 4 days remaining
Passenger lift replacementS20-2026-035 · Works £250 Beaufort Place £312,000 £5,200 15 Sep 2026 Ready to award
Grounds maintenance, 3 yearsS20-2026-033 · QLTA £100/yr Marlow Gate £78,000 £347/yr 11 Sep 2026 Nominee awaited
Communal window replacementS20-2026-029 · Works £250 Thornhill House £214,000 £3,566 24 Sep 2026 On track
Lift maintenance agreement, 5 yearsS20-2026-027 · QLTA £100/yr Ravensbourne Tower £142,000 £237/yr 2 Oct 2026 On track
Car park deck waterproofingS20-2026-024 · Works £250 Pemberton Wharf £211,000 £2,344 19 Sep 2026 On track
Stage columns read left to right: Notice of Intention · observation · estimates · observation · award. Two triggers, two tests: qualifying works consult above £250 per leaseholder in total; qualifying long-term agreements consult above £100 per leaseholder per year. The system applies whichever test the agreement type calls for.