Rao — 22 Marlow Rise, Ipswich
JOB-4471 · 8.8 kW & 10 kWh battery · quoted 24 Jun · installed 15 Jul · Tuilagi crew
Certificates blocked
Customer paid
$16,800
$19,650 less certificates
Certificate value
$2,850
Not yet created
Margin at risk
$2,180
Becomes −$1,010 if certificates fail
Meter reconfiguration
40 days
Customer exporting for nothing
Everything that happened
Quote to today · 62 days
- Enquiry
- Site assessment
- Quote accepted, certificates assigned
- Grid connection applied for
- Approved at 5 kW export
- Installed and energised
- Electrical certificate lodged
- Meter reconfiguration requested
- Evidence pack short
- Certificates created
Nobody noticed the pack was short for 24 days. It surfaced when Chantelle worked through a backlog, not when the crew closed the job. Twenty-four days is long enough for the crew to have been past the house four times.
The system
Still owed to the customer
Meter reconfigured40 days
Monitoring set upDone
Handover packSent 17 Jul
Warranty registeredDone
The Raos have been exporting to the grid for forty days without being paid for it. That is the retailer's doing, not Wattlebank's — but Wattlebank is who they will ring, and nobody has told them what is happening.
Design and grid approval
What was applied for, what came back, and what the customer was told
| Item | Proposed | Approved | Customer told | Status |
|---|---|---|---|---|
| Array size | 8.8 kW | 8.8 kW | 28 Jun | As sold |
| Inverter | 8 kW hybrid | 8 kW hybrid | 28 Jun | As sold |
| Battery | 10 kWh | 10 kWh | 28 Jun | As sold |
| Export limit | 10 kW requested | 5 kW granted | 2 Jul | Told same day |
| Estimated first-year saving | $2,140 | $1,880 at 5 kW | 2 Jul | Revised and sent |
This job handled the export limit properly — applied for 10 kW, got 5 kW, told the customer the same day and reissued the savings estimate. Six complaints last year were jobs where that did not happen.
Job documents
18 held · everything filed against what it evidences
| Document | Evidences | Added | By | Status |
|---|---|---|---|---|
| Signed quote & written statement | Certificate assignment | 28 Jun | F. Achieng | Held |
| Grid connection approval | Permission to connect | 2 Jul | Automatic | Held |
| Installer check-in / check-out | Accredited installer on site | 15 Jul | W. Tuilagi | Geotagged |
| Panel serial photographs | Components installed | 15 Jul | W. Tuilagi | 6 unreadable |
| Array photograph | Panel count and layout | 15 Jul | W. Tuilagi | Not usable |
| Battery serial | Component installed | — | — | Missing |
| Electrical certificate | Electrical compliance | 16 Jul | W. Tuilagi | Lodged |
| Handover pack | Operation and warranty | 17 Jul | B. Nguyen | Sent |
| Revised savings estimate | 5 kW export limit | 2 Jul | F. Achieng | Sent |
Sixteen of eighteen documents are perfect. The two that are not are the two that decide whether $2,850 exists.